Sunday, June 12, 2011

Forming fun with Kyla

It was so nice to hear that Kyla was coming up for the weekend to give me a hand.  We really got a lot accomplished.

We started on the footings for the shop 

Between rains we almost got the footings finished by Saturday dinner time.

Kyla measuring for 16 inches and nailing cross-bracing
Finished forms

Then we tackled the front step footings for the last of the timber installation.
First we had to remove the temporary 2 x 6 posts 
Our big task was changing the posts to get them out of the way
Digging the holes for the foundations
One of the boxes for concrete ready with rebar, thanks to Kyla.
Our new split entrance
Tomorrow I will get some rebar for the shop footings and have a visit with the engineer to approve the job.  The concrete arrives on Tuesday so I'll have to be ready.

Goodnight and thank you Kyla a whole bunch.

1 comment:

  1. I'm curious about some of the order of assembly items. For example, I notice the basement floor is not done and then things like these footings for the entry - I would have thought they would have happened with other footing work.
    Did Tamlin provide project plan advice for sequencing and such?

    ReplyDelete