Lots going on these days. I have been doing a fair bit of digging to prep the site for the shop foundation. This is a bit of a priority as we will need the space for our furniture in a month or so.
After all the trees were de-limbed and cut up the branches were stacked waiting for the chipper. A company in town now rents one so we reserved it. I will be moving the log sections out of the way for splitting later.
|
Piles along the driveway |
|
From the two trees that were dropped in the yard |
The chipping went a lot smoother than last year and I was able to get it back for a half day fee.
|
Mrs Fargo |
|
Mr Fargo |
|
A lot of useful chips |
Our next ongoing project will be the parging. This is a transition concrete type of product for the siding to start at and the dirt to end at. It is applied over the moisture barrier that goes down to the footings.
|
I apply the first coat |
|
Cath is working in the fiberglass mesh |
|
First coat with mesh completed to the corner |
Another task that was overdue was the culvert for our driveway. The backhoe performed quite well for this job.
|
I'm getting the hang of this thing |
|
Just cover it over and voila |
|
I shouldn't hear any more comments from my neighbour |
It decided to rain for 6 hours over night and that means no digging. We packed up and went home where I loaded the truck and trailer for the return trip.
I always prepare for the worst in weather but this trip was nice and dry. It took an hour and a half to unload and then it started to sprinkle. It's been raining on and off for a couple of hours now. If it gets too wet again I will be starting on the stairs for the garage room.